Merrill Field Pounding Expected to Last Through September
ANCHORAGE (KTUU)
Six days a week, there’s a constant pounding sound coming from the
Merrill Field Airport during the day. It’s a 15 ton steel-encased
concrete block in free fall, hitting the ground from seven stories up.
Airport manager Paul Bowers said it's part of a unique trash compacting construction job to repave nearly eight acres of of taxiway that’s sinking into the ground of what used to be the original city dump.
“There are car bodies in here, broken buildings, broken roads, furniture,” said Bowers. “Right now, we're standing on about 25 feet of trash.”
Construction costs are about $6.9 million, primarily paid for through federal funds.
Officials said fixing up the taxiway is important because it connects the hospital to those being flown into Anchorage on emergency flights.
“Merrill field is one of the few airports in the nation with a taxiway that actually accommodates medevac aircraft going to an adjacent hospital,” said Bowers.
The concrete block compacts the trash down about eight feet. Once the entire area is smashed down, the ground will be smoothed, leveled and paved. The compacted road is expected to last about 15 years before it runs the possibility of sinking and warping again.
This trash compacting project is part of a multi-phase, multi-year effort to smooth out the roads and taxiways at Merrill Field.
Airport manager Paul Bowers said it's part of a unique trash compacting construction job to repave nearly eight acres of of taxiway that’s sinking into the ground of what used to be the original city dump.
“There are car bodies in here, broken buildings, broken roads, furniture,” said Bowers. “Right now, we're standing on about 25 feet of trash.”
Construction costs are about $6.9 million, primarily paid for through federal funds.
Officials said fixing up the taxiway is important because it connects the hospital to those being flown into Anchorage on emergency flights.
“Merrill field is one of the few airports in the nation with a taxiway that actually accommodates medevac aircraft going to an adjacent hospital,” said Bowers.
The concrete block compacts the trash down about eight feet. Once the entire area is smashed down, the ground will be smoothed, leveled and paved. The compacted road is expected to last about 15 years before it runs the possibility of sinking and warping again.